Question 3065 of 344 · NICET Fire Alarm Systems Level II
A design shows a notification zone layout for partial evacuation. Which information must the drawings make clear?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 3065
- A: Which appliances belong to each notification zone
Explanation
Where partial or staged evacuation is used, the drawings and sequence of operation must show the notification zones so reviewers can confirm that the right areas receive the right messages.
More questions: Submittal Preparation and System Layout
- 3066What is the main purpose of a fire alarm system's sequence of operation for the AHJ?
- 3067A design places a spot smoke detector 2 ft from a supply diffuser. What should the reviewer note?
- 3068A design calls for a sidewall mounted smoke detector. What placement must the drawing show?
- 3069Which standby duration does NFPA 72 require for the secondary power of an emergency voice/alarm communication system in alarm?
- 3070Which equipment locations must the shop drawings show besides initiating devices and appliances?
- 3071When should fire alarm shop drawings normally be approved by the AHJ?