Under AIA A201 (2017), what does the architect's review of shop drawings check?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4013
- B: Conformance with the design concept of the contract documents
Explanation
The architect reviews submittals only for the limited purpose of checking conformance with information given and the design concept. The contractor remains responsible for dimensions, quantities, and means and methods.
More questions: Management and Supervision
- 4014Under AIA A201 (2017), what must the contractor do before submitting shop drawings to the architect?
- 4015Under AIA A201 (2017), which document changes the contract sum or time and is signed by the owner, contractor, and architect?
- 4016Under AIA A201 (2017), what allows the owner to direct a change before the price is agreed?
- 4017Under AIA A201 (2017), who may order a minor change in the work that does not change the contract sum or time?
- 4018Under AIA A201 (2017), within how many days after the event must a claim normally be started?
- 4019Under AIA A201 (2017), how long is the correction period after substantial completion?