Question 4014 of 344 · NICET Fire Alarm Systems Level II
Under AIA A201 (2017), what must the contractor do before submitting shop drawings to the architect?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4014
- C: Review, approve, and coordinate them
Explanation
By submitting shop drawings, the contractor represents that it has reviewed and approved them, checked field measurements, and coordinated them with the contract documents and other submittals.
More questions: Management and Supervision
- 4015Under AIA A201 (2017), which document changes the contract sum or time and is signed by the owner, contractor, and architect?
- 4016Under AIA A201 (2017), what allows the owner to direct a change before the price is agreed?
- 4017Under AIA A201 (2017), who may order a minor change in the work that does not change the contract sum or time?
- 4018Under AIA A201 (2017), within how many days after the event must a claim normally be started?
- 4019Under AIA A201 (2017), how long is the correction period after substantial completion?
- 4020Under AIA A201 (2017), who is solely responsible for construction means, methods, techniques, sequences, and procedures?