Question 4014 of 344 · NICET Fire Alarm Systems Level II

Under AIA A201 (2017), what must the contractor do before submitting shop drawings to the architect?

Exactly one answer is correct.

Show solution

Correct answer to question 4014

  • C: Review, approve, and coordinate them

Explanation

By submitting shop drawings, the contractor represents that it has reviewed and approved them, checked field measurements, and coordinated them with the contract documents and other submittals.

Next to question ›