Question 4016 of 344 · NICET Fire Alarm Systems Level II

Under AIA A201 (2017), what allows the owner to direct a change before the price is agreed?

Exactly one answer is correct.

Show solution

Correct answer to question 4016

  • B: A construction change directive

Explanation

A construction change directive is signed by the owner and architect and directs a change in the work before the contract sum or time adjustment is agreed. The contractor proceeds while the adjustment is settled.

Next to question ›