Under AIA A201 (2017), what allows the owner to direct a change before the price is agreed?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4016
- B: A construction change directive
Explanation
A construction change directive is signed by the owner and architect and directs a change in the work before the contract sum or time adjustment is agreed. The contractor proceeds while the adjustment is settled.
More questions: Management and Supervision
- 4017Under AIA A201 (2017), who may order a minor change in the work that does not change the contract sum or time?
- 4018Under AIA A201 (2017), within how many days after the event must a claim normally be started?
- 4019Under AIA A201 (2017), how long is the correction period after substantial completion?
- 4020Under AIA A201 (2017), who is solely responsible for construction means, methods, techniques, sequences, and procedures?
- 4021Under AIA A201 (2017), what may the architect do with a submittal that the contract documents do not require?
- 4022A Level II technician finds a conflict between the fire alarm drawings and the ceiling plan. What is the correct way to resolve it?