Question 4015 of 344 · NICET Fire Alarm Systems Level II

Under AIA A201 (2017), which document changes the contract sum or time and is signed by the owner, contractor, and architect?

Exactly one answer is correct.

Show solution

Correct answer to question 4015

  • A: A change order

Explanation

A change order is a written instrument signed by all three parties that states the agreed change in work, contract sum, and contract time.

Next to question ›