Question 4017 of 344 · NICET Fire Alarm Systems Level II

Under AIA A201 (2017), who may order a minor change in the work that does not change the contract sum or time?

Exactly one answer is correct.

Show solution

Correct answer to question 4017

  • D: The architect

Explanation

The architect may order minor changes consistent with the intent of the contract documents that do not involve a change in contract sum or time. These are binding on owner and contractor.

Next to question ›