Under AIA A201 (2017), who may order a minor change in the work that does not change the contract sum or time?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4017
- D: The architect
Explanation
The architect may order minor changes consistent with the intent of the contract documents that do not involve a change in contract sum or time. These are binding on owner and contractor.
More questions: Management and Supervision
- 4018Under AIA A201 (2017), within how many days after the event must a claim normally be started?
- 4019Under AIA A201 (2017), how long is the correction period after substantial completion?
- 4020Under AIA A201 (2017), who is solely responsible for construction means, methods, techniques, sequences, and procedures?
- 4021Under AIA A201 (2017), what may the architect do with a submittal that the contract documents do not require?
- 4022A Level II technician finds a conflict between the fire alarm drawings and the ceiling plan. What is the correct way to resolve it?
- 4023Before acceptance testing of elevator recall and shunt trip, which coordination is needed?