Question 1077 of 297 · NICET Fire Alarm Systems Level III
The HVAC contractor has not yet started the air handlers when the fire alarm acceptance test is scheduled. What should the Level III project lead do?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1077
- C: Reschedule or coordinate so the fan shutdown and damper functions can be observed working
Explanation
Acceptance testing must prove that emergency control functions actually operate the controlled equipment. Testing only the relay contact does not show that the fan stops or the damper closes, so the test must be coordinated with the trades that control the equipment.
More questions: Installation
- 1078Before final inspection, the sprinkler contractor asks to monitor the fire pump. Which conditions are typically supervised at the fire alarm system for an electric fire pump?
- 1079Which of the following is the best way to deal with a scope gap discovered mid-project, where the contract drawings show no detection in a new IT room that the code requires?
- 1080Why should a Level III verify the listing of every substituted device before it is installed?
- 1081During rough-in inspection on a new office building, you find several fire alarm junction boxes above a hard lid ceiling with no access panel. What is the main concern?
- 1082A fire alarm interface relay will release the hold-open power for corridor smoke doors. How should the release be wired so it is fail-safe?
- 1083On a project where the AHJ requires a fire watch during the cutover from the old system to the new one, who is normally responsible for providing it?