Which of the following is the best way to deal with a scope gap discovered mid-project, where the contract drawings show no detection in a new IT room that the code requires?

Exactly one answer is correct.

Show solution

Correct answer to question 1079

  • B: Notify the engineer or owner in writing and request direction or a change order before adding work

Explanation

Code compliance problems in the design need to be raised formally so the responsible design professional and owner can decide, and so cost and schedule impacts are handled through a change order. Quietly adding or ignoring work creates both code and contract problems.