Question 1010 of 243 · NICET Fire Alarm Systems Level IV
Before starting the annual test of a monitored system in a hotel, which step does NFPA 72 require regarding signal recipients?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1010
- B: Notify the supervising station and all other facilities and people who receive alarm, supervisory or trouble signals
Explanation
Before testing, everyone who receives signals or whose operations are affected must be notified so that test signals are not treated as real events. Disconnecting the communicator would defeat testing of the transmission path. The same people must be told when testing is complete.
More questions: Installation, Planning and Maintenance Management
- 1011A data center fire alarm system interfaces with a preaction releasing panel, HVAC shutdown and door unlocking. What must be in place before the periodic test begins?
- 1012Under the International Fire Code, a required fire alarm system is out of service. What must happen?
- 1014A fire alarm contractor agrees to install a high-rise voice system for a fixed total price regardless of the actual cost. Which contract type is this, and who carries the risk of cost overruns?
- 1015An owner wants to pay the contractor's actual costs plus a fee, but with a ceiling the price cannot exceed. Which contract arrangement fits?
- 1016A campus retrofit is priced at a fixed amount per installed device because the final device count is not known at bid time. Which contract type is this?
- 1017The general contractor withholds 10 percent of each progress payment from the fire alarm subcontractor until the project is accepted. What is this withheld money called?