Question 1003 of 243 · NICET Fire Alarm Systems Level IV

Under the commissioning process described in NFPA 3, who normally develops the owner's project requirements (OPR)?

Exactly one answer is correct.

Show solution

Correct answer to question 1003

  • C: The owner, with help from the commissioning authority if one is engaged

Explanation

The OPR captures what the owner needs from the systems, so it originates with the owner, often facilitated by the commissioning authority. Contractors and the AHJ respond to it rather than write it.