Question 1039 of 344 · NICET Fire Alarm Systems Level II

Before installing devices on a new project, what is the first document a Level II technician should compare against field conditions to build a work plan?

Exactly one answer is correct.

Show solution

Correct answer to question 1039

  • D: The approved shop drawings and specifications

Explanation

Work plans start from the approved shop drawings and the project specifications. Field conditions such as obstructions, ceiling heights, and air diffusers are compared to the drawings, and conflicts are raised before work starts.