Question 1040 of 344 · NICET Fire Alarm Systems Level II

During rough-in, the technician finds that a duct now sits where a smoke detector is shown on the approved drawing. What is the correct action?

Exactly one answer is correct.

Show solution

Correct answer to question 1040

  • A: Report it and get an approved revision first

Explanation

Field changes to an approved design must go through the designer and, where required, the AHJ. Relocating a device can affect spacing and coverage, so the change is documented and approved before installation.