Question 1097 of 344 · NICET Fire Alarm Systems Level II
Which records must be completed for a new system and given to the owner after acceptance?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1097
- A: Record of completion, record drawings, and test records
Explanation
After acceptance, the owner receives the completed record of completion, record (as built) drawings, the sequence of operations, manuals, and the acceptance test records.
More questions: Installation
- 1098In a corridor not more than 20 ft wide, how far apart may visible appliances be spaced under the corridor rule of NFPA 72 (2022)?
- 1099A wall mounted visible appliance must cover a 20 ft by 20 ft room by itself. What minimum effective intensity does the wall mounted room table require?
- 1100A 40 ft by 40 ft room will be covered by one wall mounted strobe. What minimum effective intensity does the wall mounted room table require?
- 1101Which control function is commonly wired from a fire alarm relay to release magnetically held smoke doors?
- 1102Where must the relay or control module that operates an emergency control function be located?
- 1103How are HVAC fan shutdown circuits typically installed when they are not monitored for integrity?